Case Study: Brisbane Airport Corporation Multi Level Car Park
When ADCO Constructions was appointed Builder of Choice for the Brisbane Airport Corporation Multi Level Car Park, they chose to partner with our experienced 1300TempFence Queensland team to help deliver a safe, reliable and flexible site safety solutions across this complex, multi-level project.
This $90 million car park expansion includes a six-level structure that will seamlessly connect to the existing P2 car park. Once complete, the extension will provide at least 1,700 additional long-term parking spaces, significantly increasing the airport’s parking capacity and reducing congestion during peak travel periods.
With construction taking place in a live airport environment and across multiple elevated levels, ADCO required a specialist partner capable of delivering compliant, durable and efficiently installed site safety systems. Our team provided a tailored solution to meet the project’s strict requirements, operational constraints, and tight delivery milestones.
Our site safety and temporary fencing solution
- 1300TempFence supplied and carried out staged installs across the six levels of the multi-storey structure installing
- 338 Shield 1 barriers with fence toppers for safe pedestrian and vehicle separation
- 677m of temporary fencing, professionally braced every third panel for enhanced stability and compliance
These installations formed a critical safety measure for workers, trades and airport personnel as construction progressed across all levels of the building.
Delivering in a high-security, high-traffic airport environment
Working within Brisbane Airport’s operational footprint required meticulous planning and seamless coordination. Our team successfully navigated the complexities of:
- Strict timeframes & staged installs; Early-morning access requirements meant crews were onsite from 3am to 6am to complete key stages before peak airport activity.
- Multi-level access constraints; Moving equipment and materials safely across six levels demanded precise scheduling and constant communication with ADCO and other onsite partners.
- Coordination with multiple trades; Our installations were delivered without disrupting ADCO’s broader construction program, ensuring safe and efficient workflows throughout the project.
Despite the challenges, every stage was delivered on time, safely, and without any impact to airport operations.
The success of this project was led by our Site Supervisor, Brett Walsh, whose hands-on coordination, clear communication and proactive problem-solving helped ADCO achieve their program milestones.
Brett worked closely with ADCO to manage expectations, respond quickly to changing site conditions, and ensure seamless installation across all levels. His professionalism and adaptability were highly valued by the ADCO team, who commended the quality of our temporary fencing, barrier systems, and overall project delivery.
Why ADCO trusted 1300TempFence
- Proven experience in complex, high-security environments
- Ability to deliver large-scale installations under tight timeframes
- Strong onsite communication and leadership
- High-quality, compliant and reliable site safety products
Whether it’s an airport project, major infrastructure build or multi-stage commercial development, 1300TempFence delivers safe, compliant and dependable site solutions on time, every time.
Need a trusted partner for your next project?
Speak with our experienced team today. Call 1300 836 733 for site safety and temporary fencing solutions you can rely on.